1. **State the problem:**
We know 9 men produce 30 pans in 6 days. We want to find how long 12 men will take to produce 42 pans at the same work rate.
2. **Formula and concept:**
Work done = Number of men × Number of days × Rate per man
Since rate per man is constant, work is proportional to men × days.
3. **Calculate the total work done by 9 men:**
Work = 9 men × 6 days = 54 man-days to produce 30 pans.
4. **Find work per pan:**
Work per pan = 54 man-days / 30 pans = 1.8 man-days per pan.
5. **Calculate total work needed for 42 pans:**
Total work = 42 pans × 1.8 man-days per pan = 75.6 man-days.
6. **Find how many days 12 men need to do 75.6 man-days:**
Days = Total work / Number of men = 75.6 / 12 = 6.3 days.
**Final answer:**
It will take 12 men approximately $6.3$ days to produce 42 pans at the same rate.
Men Pans Time 145F9F
Step-by-step solutions with LaTeX - clean, fast, and student-friendly.