1. **State the problem:** We know 8 men can complete a work in 12 days. We need to find how many days 6 men will take to complete the same work.
2. **Understand the relationship:** The amount of work done is constant. Work done = Number of men × Number of days.
3. **Calculate total work:** Total work = $8 \times 12 = 96$ man-days.
4. **Find days for 6 men:** Let the number of days for 6 men be $x$. Then, $6 \times x = 96$.
5. **Solve for $x$:**
$$x = \frac{96}{6} = 16$$
6. **Conclusion:** 6 men will take 16 days to complete the work.