1. Problem 14: A contractor has 560 workers to complete a stadium part in 9 months but now must finish in 5 months. Find extra workers needed.
2. Use the work formula: Work = Number of workers \times Time.
3. Original work: $560 \times 9 = 5040$ worker-months.
4. New time: 5 months, so workers needed: $\frac{5040}{5} = 1008$.
5. Extra workers: $1008 - 560 = 448$.
6. Problem 15: Geeta types 108 words in 6 minutes. Find words typed in 30 minutes.
7. Words per minute: $\frac{108}{6} = 18$.
8. Words in 30 minutes: $18 \times 30 = 540$.
9. Problem 16: $l$ varies directly as $m$.
10. i) Equation: $l = km$.
11. ii) Given $l=6$, $m=18$, find $k$: $6 = k \times 18 \Rightarrow k = \frac{6}{18} = \frac{1}{3}$.
12. iii) Find $l$ when $m=33$: $l = \frac{1}{3} \times 33 = 11$.
13. Problem 17: Deposit 2000 earns 500 interest in 3 years. Find interest on 36000 in 3 years at same rate.
14. Simple interest formula: $I = PRT$.
15. Rate $R = \frac{I}{PT} = \frac{500}{2000 \times 3} = \frac{500}{6000} = \frac{1}{12}$.
16. Interest on 36000: $I = 36000 \times \frac{1}{12} \times 3 = 9000$.
17. Problem 18: Mass varies directly with length.
18. Given: length 16 cm, mass 192 g.
19. Relation: $m = kl$.
20. Find $k$: $192 = k \times 16 \Rightarrow k = 12$.
21. Find length for mass 105 g: $105 = 12 \times l \Rightarrow l = \frac{105}{12} = 8.75$ cm.
22. Problem 19: Naresh walks 250 steps for 200 m. Find distance for 350 steps.
23. Distance per step: $\frac{200}{250} = 0.8$ m.
24. Distance for 350 steps: $0.8 \times 350 = 280$ m.
25. Problem 20: Car travels 225 km in 25 litres. Find litres for 540 km.
26. Fuel efficiency: $\frac{225}{25} = 9$ km/litre.
27. Litres for 540 km: $\frac{540}{9} = 60$ litres.
28. Problem 21: $a$ and $b$ vary inversely: $a \times b = k$.
29. i) Table 1:
- For $a=2$, $b=x$: $2 \times x = k$.
- For $a=6$, $b=15$: $6 \times 15 = 90 = k$.
- So $k=90$.
- Find $x$: $2x=90 \Rightarrow x=45$.
- Find $y$ when $b=12.5$: $y \times 12.5=90 \Rightarrow y=\frac{90}{12.5}=7.2$.
- Find $z$ when $a=10$: $10 \times z=90 \Rightarrow z=9$.
30. ii) Table 2:
- For $a=6$, $b=18$: $6 \times 18=108=k$.
- For $a=8$, $b=P$: $8P=108 \Rightarrow P=13.5$.
- For $a=Q$, $b=39$: $Q \times 39=108 \Rightarrow Q=\frac{108}{39} \approx 2.77$.
- For $a=25$, $b=r$: $25r=108 \Rightarrow r=4.32$.
31. Problem 22: Cloth cost Rs 337.50 for 25 m.
32. i) Cost per meter: $\frac{337.5}{25} = 13.5$.
33. Cost for 40 m: $13.5 \times 40 = 540$.
34. ii) Length for Rs 675: $\frac{675}{13.5} = 50$ m.
Final answers:
14) Extra workers = 448
15) Words in 30 min = 540
16) i) $l=km$, ii) $k=\frac{1}{3}$, iii) $l=11$
17) Interest = 9000
18) Length = 8.75 cm
19) Distance = 280 m
20) Petrol = 60 litres
21) i) $x=45$, $y=7.2$, $z=9$; ii) $Q=2.77$, $P=13.5$, $r=4.32$
22) i) Cost = 540, ii) Length = 50