1. **State the problem:**
Calculate the safety inventory given the lead time, average weekly usage, and maximum weekly usage.
2. **Formula used:**
Safety inventory is calculated as:
$$\text{Safety Inventory} = (\text{Maximum Weekly Usage} - \text{Average Weekly Usage}) \times \text{Lead Time}$$
3. **Substitute the values:**
$$= (90 - 70) \times 9$$
4. **Calculate the difference:**
$$= 20 \times 9$$
5. **Multiply to find safety inventory:**
$$= 180$$
6. **Interpretation:**
The safety inventory is 180 units, which means you should keep 180 units as a buffer to cover fluctuations in demand during the lead time.
**Final answer:** 180 units.
Safety Inventory Cffa78
Step-by-step solutions with LaTeX - clean, fast, and student-friendly.