1. **State the problem:**
We have a project with multiple jobs and their time estimates: optimistic ($t_0$), most likely ($t_m$), and pessimistic ($t_p$). We need to draw the project network and find the probability of completing the project in 40 days.
2. **Calculate the expected time ($t_e$) and variance ($\sigma^2$) for each job:**
The expected time is given by $$t_e = \frac{t_0 + 4t_m + t_p}{6}$$
The variance is $$\sigma^2 = \left(\frac{t_p - t_0}{6}\right)^2$$
3. **List the jobs and their times:**
| Job | $t_0$ | $t_m$ | $t_p$ |
|-----|-------|-------|-------|
| 1-2 | 1 | 7 | 13 |
| 1-6 | 4 | 5 | 5 |
| 2-3 | 2 | 5 | 14 |
| 2-4 | 2 | 14 | 8 |
| 3-5 | 2 | 5 | 3 |
| 6-7 | 7 | 10 | 17 |
| 5-8 | 6 | 5 | 26 |
| 7-8 | 5 | 3 | 8 |
4. **Calculate $t_e$ and $\sigma^2$ for each job:**
- Job 1-2: $t_e = \frac{1 + 4(7) + 13}{6} = \frac{1 + 28 + 13}{6} = \frac{42}{6} = 7$; $\sigma^2 = \left(\frac{13 - 1}{6}\right)^2 = \left(\frac{12}{6}\right)^2 = 2^2 = 4$
- Job 1-6: $t_e = \frac{4 + 4(5) + 5}{6} = \frac{4 + 20 + 5}{6} = \frac{29}{6} \approx 4.83$; $\sigma^2 = \left(\frac{5 - 4}{6}\right)^2 = \left(\frac{1}{6}\right)^2 = 0.0278$
- Job 2-3: $t_e = \frac{2 + 4(5) + 14}{6} = \frac{2 + 20 + 14}{6} = \frac{36}{6} = 6$; $\sigma^2 = \left(\frac{14 - 2}{6}\right)^2 = 2^2 = 4$
- Job 2-4: $t_e = \frac{2 + 4(14) + 8}{6} = \frac{2 + 56 + 8}{6} = \frac{66}{6} = 11$; $\sigma^2 = \left(\frac{8 - 2}{6}\right)^2 = 1^2 = 1$
- Job 3-5: $t_e = \frac{2 + 4(5) + 3}{6} = \frac{2 + 20 + 3}{6} = \frac{25}{6} \approx 4.17$; $\sigma^2 = \left(\frac{3 - 2}{6}\right)^2 = \left(\frac{1}{6}\right)^2 = 0.0278$
- Job 6-7: $t_e = \frac{7 + 4(10) + 17}{6} = \frac{7 + 40 + 17}{6} = \frac{64}{6} \approx 10.67$; $\sigma^2 = \left(\frac{17 - 7}{6}\right)^2 = \left(\frac{10}{6}\right)^2 = 2.78$
- Job 5-8: $t_e = \frac{6 + 4(5) + 26}{6} = \frac{6 + 20 + 26}{6} = \frac{52}{6} \approx 8.67$; $\sigma^2 = \left(\frac{26 - 6}{6}\right)^2 = \left(\frac{20}{6}\right)^2 = 11.11$
- Job 7-8: $t_e = \frac{5 + 4(3) + 8}{6} = \frac{5 + 12 + 8}{6} = \frac{25}{6} \approx 4.17$; $\sigma^2 = \left(\frac{8 - 5}{6}\right)^2 = \left(\frac{3}{6}\right)^2 = 0.25$
5. **Draw the project network:**
The network nodes and jobs are:
- Start at 1
- Jobs: 1-2, 1-6
- From 2: jobs 2-3, 2-4
- From 3: job 3-5
- From 6: job 6-7
- From 5: job 5-8
- From 7: job 7-8
- End at 8
6. **Find all paths from start (1) to end (8) and their expected durations:**
- Path 1: 1-2-3-5-8
$$7 + 6 + 4.17 + 8.67 = 25.84$$
- Path 2: 1-2-4 (ends at 4, no path to 8, discard)
- Path 3: 1-6-7-8
$$4.83 + 10.67 + 4.17 = 19.67$$
7. **Identify the critical path:**
The longest expected duration path is 1-2-3-5-8 with $25.84$ days.
8. **Calculate the variance of the critical path:**
Sum variances of jobs on critical path:
$$4 + 4 + 0.0278 + 11.11 = 19.14$$
9. **Calculate the standard deviation of the critical path:**
$$\sigma = \sqrt{19.14} \approx 4.38$$
10. **Calculate the Z-score for completing in 40 days:**
$$Z = \frac{40 - 25.84}{4.38} = \frac{14.16}{4.38} \approx 3.23$$
11. **Find the probability:**
Using standard normal distribution tables, $P(Z \leq 3.23) \approx 0.9993$.
**Final answer:**
The probability of completing the project in 40 days is approximately **99.93%**.
Project Completion
Step-by-step solutions with LaTeX - clean, fast, and student-friendly.